The restoration is now picking up pace with the fabrication of the regulator lever assembly and its fitment to the boiler backhead. The main steam pipes have now been assembled in the smokebox.

The restoration is now picking up pace with the fabrication of the regulator lever assembly and its fitment to the boiler backhead. The main steam pipes have now been assembled in the smokebox.

A major milestone has been reached with the completion of the main steam pipe as in our picture whilst the smokebox acts as a scheduling board for work to be completed in August.

While the work on the NG10 continues, the team working on the 4AR, number 1555 for Transnet are making good progress with the locomotive and tender now stripped and cleaned and the application of the red ochre preservative paint starting to be applied.

As the myriad of smaller tasks continues the reverser handle has been completed and fitted together with the reversing mechanism. The vacuum ejector and piping has also been assembled and fitted but the train pipes are still to be attached.
